Question ID 7069

Scenario Please read this scenario prior to answering the Question Your role is that of a consultant to the Lead Enterprise Architect in a company that develops photovoltaic technologies for use in large-scale solar power farms. The company has three manufacturing facilities, two in the United States, and one in Southern France. Each of these facilities supplies a different manufacturer that assembles and sells complete systems. The solar panels and photovoltaic arrays are custom engineered to meet each manufacturer's design specifications. A challenge that the solar power industry has faced is the efficiency of energy conversion. When a conventional solar panel overheats, it becomes inefficient and generates less energy. In response to this, the research arm of the company has pioneered the development of a new solar panel design that will produce up to 50% more energy than standard solar panels when operating at elevated temperatures. This will allow the production of significantly more useable energy per square meter than from standard solar technology. This new design is ready to go into production. The company has a mature Enterprise Architecture practice that is supported by a cross-functional Architecture Board. TOGAF 9 is used for developing the automated manufacturing process and systems used to design, manufacture and test the solar power technologies they produce. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program. As part of putting the new solar panel design into production, a pilot architecture project at a single location has defined an updated standard approach for controlling the automated test systems used to perform final quality assurance. The Chief Engineer, sponsor of the activity, and the Architecture Board have approved the plan for immediate implementation at each plant. Architecture Contracts have been developed that detail the work needed to implement and deploy the new automated test system controller for each location. The Chief Engineer has expressed concern that a uniform process be employed at each location to ensure consistency and high yields. Refer to the Scenario The Lead Enterprise Architect has asked you to recommend the best approach to address the Chief Engineer's concern. Based on TOGAF, which of the following is the best answer?

Option A

You review the applicable Architecture Contract for each location, ensuring that it addresses the project objectives, effectiveness metrics, acceptance criteria, and risk management. In cases where the contract is issued to an external party, you ensure that it is a legally enforceable contract. You schedule compliance reviews at key points in the implementation process to ensure that the work is proceeding in accordance with the Architecture Definition. You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.

Option B

You create an Architecture Contract to manage and govern the implementation and migration process at each location. For internal development projects, you issue a memorandum of understanding between the Architecture Board and the implementation organization. For contracts issued to an external party, you ensure that it is a fully enforceable legal contract. You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.

Option C

You create an Architecture Contract to manage and govern the implementation and migration process. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contract. For internal development projects, you decide it Is adequate to utilize a memorandum of understanding between the Architecture Board and the implementation organization. You recommend that if a deviation from the Architecture Contract is detected, the Architecture Board grant a dispensation to allow the implementation organization the ability to customize the process to meet their local needs.

Option D

You use the Architecture Contracts to manage the architecture governance processes for the project across the locations. You deploy monitoring tools to assess the performance of each completed solar panel assembly at each location and develop change requirements if necessary. You recommend that if a deviation from the contract is detected, the Architecture Board should modify the Architecture Contract to allow the implementation organization the ability to customize the process to meet their local needs. As a result, you then issue a new Request for Architecture Work to implement the modified Architecture Definition.

Correct Answer A
Explanation


Question ID 7070

Scenario Please read this scenario prior to answering the Question You have been assigned the role of Chief Enterprise Architect within a leading outsourcing services company. The company has over 20,000 outsourcing professionals and works on some of the world's largest outsourcing projects. Outsourcing services include business processes, infrastructure, and service management. The company also provides business consulting services. With numerous service areas and a large number of diverse engagements in progress at any given time, overall engagement management within the company has become challenging. The company does not want to risk Its outstanding reputation or its international certifications and CMM ratings. The company has an established an Enterprise Architecture program based on TOGAF 9, sponsored jointly by the Chief Executive Officer and Chief Information Officer. An Architecture Board has been formed comprised of IT staff executives and executives from the major service areas and consulting practice. The Enterprise Architecture (EA) team has been working with the Strategic Planning team to create a strategic enterprise architecture to address these issues. The EA team has defined a framework and held workshops with key stakeholders to define a set of architecture principles to govern the architecture work. They have completed an Architecture Vision at a strategic level and laid out Architecture Definitions for the four domains. They have set out an ambitious vision of the future of the company over a five-year period. This includes a solution architecture including three distinct transformations. The CIO has made it clear that prior to the approval of the detailed Implementation and Migration plan, the EA team will need to assess the risks associated with the proposed architecture. He has received concerns from some of the vice presidents across the company that the proposed architecture may be too ambitious and they are not sure it can produce sufficient value to warrant the attendant risks. Refer to the Scenario You have been asked to recommend an approach to satisfy these concerns. Based on TOGAF, which of the following is the best answer?

Option A

The EA team should gather information about potential solutions from the appropriate sources. Once the Solution Architecture has been assembled, it should be analyzed using a state evolution table to determine the Transition Architectures. A value realization process should then be established to ensure that the concerns raised are addressed.

Option B

Before preparing the detailed Implementation and Migration plan, the EA team should review and consolidate the gap analysis results from Phases B to D to understand the transformations that are required to achieve the proposed Target Architecture. The EA team should then assess the readiness of the organization to undergo change. Once the Solution Architecture has been assembled, it should be analyzed using a state evolution table to determine the Transition Architectures.

Option C

The EA team should apply an interoperability analysis to evaluate any potential issues across the Solution Architecture. This should include the development of a matrix showing the interoperability requirements. Once all of the concerns have been resolved, the EA team should finalize the Architecture Roadmap and the Implementation and Migration Plan.

Option D

The EA team should apply the Business Transformation Readiness Assessment technique. This will allow the risks associated with the transformations to be identified and mitigated for. It will also identify improvement actions to be worked into the Implementation and Migration Plan. The Business Value Assessment technique should then be used to determine the business value and associated risks for the transformation.

Correct Answer D
Explanation