READ Free Dumps For Microsoft- 70-178
Question ID 10873 | You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to |
Option A | You should run the Set Baseline utility and select Set Interim Plan. Select Baseline10 in the |
Option B | You should run the Set Baseline utility and select Set Interim Plan. Select Start10/Finish10 in |
Option C | You should run the Set Baseline utility and select Set Interim Plan. Select Baseline10 in the |
Option D | You should run the Set Baseline utility and select Set Interim Plan. Select Start10/Finish10 in |
Correct Answer | C |
Question ID 10874 | You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to |
Option A | By displaying the Gantt with Timeline chart. |
Option B | By displaying the Tracking Gantt chart. |
Option C | By displaying the project calendar. |
Option D | By displaying the default Gantt chart. |
Option E | By displaying the Task Usage chart. |
Correct Answer | B |